EIA – Preliminary Procedure
table of content
General Information
Before launching an approval procedure (EIA procedure or simplified procedure) the project applicant can launch an application to carry out a preliminary procedure.
This procedure takes place on a voluntary basis and serves to support the more detailed specification of the contents of the Environmental Impact Statement.
Apart from the preliminary procedure an investor service has been laid down by law by the Amendment to the Umweltverträglichkeitsprüfungsgesetz in 2009. This means that information available at the authority can be provided to the project applicant for the project preparation.
Requirements
See Description of the subject matter.
Deadline
There are no specific time limits.
Competent Authority
- The respective competent Provincial GovernmentGerman text according to the location of the project
- For the implementation of the procedure for federal roads and high-performance railway tracks: the Federal Minister for Climate Action, Environment, Energy, Mobility, Innovation and Technology (→ BMK)
Procedure
There is no special procedure to be followed.
Documents Required
- Presentation of the outline of the project
- Concept for the Environmental Impact Statement
Expenses
The costs depend on the respective Ordinances of the Federal Provinces on levies and fees. Please ask the competent body in advance.
Legal Basis
Section 4 of the Umweltverträglichkeitsprüfungsgesetz 2000 (UVP-G 2000)
Expert Information
No expert information is available.